Overview
SPI and Environment Agency works to weld waling beams onto sheet piles ahead of a cofferdam dig. The work ran as a focused one-week programme and finished on time, ready for the excavation to start.
Scope & Methods
- Set out waling beam positions and welded brackets to the sheet piles in sequence.
- Worked along both walls to keep alignment consistent for the cofferdam tie system.
- Maintained weld quality and spacing so the beams could be installed without rework.
- Coordinated around site plant movements to keep production on programme.
Highlights
Production Pace
- One-week scope completed on schedule with no delays to cofferdam excavation.
- Continuous welding sequence kept both runs in step for beam install.
Site Coordination
- Worked safely around SPI plant and environmental constraints on site.
- Waling positions held true along the length of the sheet pile line.
Outcomes
- Waling beams and brackets ready for cofferdam dig out.
- Programme completed within the one-week window.
- Clean handover to the next phase of works.
Gallery
Sheet pile lines with welded waling brackets and full run length set out for the cofferdam.