My Portfolio

Selected projects across mechanical and construction work.

Pulteney Bridge flood defence access platform after repairs

Pulteney Bridge Flood Defence Repairs

Replaced rotten inspection covers with new aluminium ones, repainted rails, and grouted voids under the slab to stabilise the access areas.

Slip casing with Bauer shoes ready for delivery

Slip Casing with Bauer Shoes - Keller

Fabricated slip casing with Bauer shoes fitted, reusing the recovered female end to keep compatibility.

Large batch of CFA augers staged for dispatch

CFA Auger Production Run

Built 30 CFA augers across 300, 350, 400, and 450 dia sizes, plus four cutting heads per size as a matched set.

Repaired weld run on the bridge beam

Bridge Beam Weld Repair - SPI Yard

Repaired a failed beam weld in the SPI yard by removing the defect, prepping the joint, and re-welding to return the beam to service.

Sheet pile line with welded waling brackets ready for the cofferdam

Sheet Pile Waling Beams - SPI / Environment Agency

Week-long programme welding waling beams onto sheet piles ahead of the cofferdam excavation, completed on time.

Large diameter bucket rebuilt with new teeth and ledger blocks

Large Diameter Buckets - Teeth & Ledger Rebuilds

Rebuilt some of our largest buckets with new teeth and ledgers, machined and welded in-house, then fabricated three more to ship straight to site.

Sheet pile wall with welded beam brackets at the ferry terminal

Isle of Man Ferry Terminal Sheet Piles

Welded beams to sheet pile outpans, drilled and fitted tie-rod plates, and recovered over-bent curved beams to finish the tie-back system ahead of schedule.

Waste conveyors and chain elevator running after repair

Waste-to-Energy Conveyor & Internal Boiler Cooling Retrofit

Recovered RDF conveyors and a chain elevator, added reactor cooling pipework, and supported the digester during commissioning before handover to Suez.

Tie-back beams and tie rods locking sheet piles under a live rail line

Live Rail Abutment Tie-Back

Staged tie rods with welded beams and anchor plates across sheet piles so the road could be widened and a larger bridge dropped in while the rail stayed live.

Plunge column guide frame over concrete-filled pile aligning the column plumb and centred

Plunge Column Guide Frame - Fabrication & Commissioning

Guide frame sits over a concrete-filled pile to hold the structural column plumb and centred while the concrete cures, locking alignment and position.

HS2 piling site with rigs and plant maintained for continuous drilling

HS2 Piling Support - On-Site Repair & Preventive Maintenance (Keller)

Rapid repairs and a preventive maintenance schedule tuned to piling cycles. Site achieved the fastest drilling rate in the whole phase of the project and finished ahead of programme.

Bridge extension with coded welds tying new rebar into existing reinforcement

Bridge Extension - Coded Rebar Welding & NDT Pass

New rebar tie-ins welded to existing reinforcement. Completed in 2 days (planned 4). All welds passed NDT; client praised organisation and communication.

Isle of Skye ferry pier with extension tubes welded onto foundation piles

Ferry Pier Widening - Foundation Tube Extensions (SPI Piling)

Four-month tidal job: fitted backing strips and polyurethane coating off-site; on-site SMAW horizontal welds across 48 sections. Every weld passed NDT and was re-coated for marine exposure.

Knowsley Safari Park bear house with steel frame, blockwork, and cladding

Knowsley Safari Park - Bear Enclosure Build & Fit-Out

Foundations, structural steel frame, blockwork and cladding coordination, galvanised steel/mesh pens, plumbing for drinkers and sink, plus external fencing and landscaping. Delivered on time and later featured on TV.

Keller workshop vibro holder mount and fixtures ready for dispatch

Keller Workshop - Multi-Job Hardfacing & Repairs

Two-month workshop lot covering auger hardfacing, cutting head rebuilds, casing repairs, and custom jigs and fixtures (vibro holder, casing holder, platform) to keep rigs productive.

New Klemm rig canopy panels staged for finishing

Klemm Rig Canopy Rebuild & Rotary Guard

Fabricated a fresh canopy, bonnet, and rotary gates for a Klemm piling rig, repaired hydraulics, and returned it painted with new trims.

Stainless bends ready for export to Ireland

Stainless Bends & Straights - Irish Power Station

Delivered 23 bends (supplied pre-formed) and 32 straight stainless flange pieces cut, rolled, and TIG-welded in-house, shipped clean to site in Ireland.

Fabrication and install works from May 2025

Fabrication & Install - May 2025

Fit-ups and finished assemblies delivered to programme.

Rig assembly and checks from July 2025

Rig Assembly & Checks - July 2025

Assembly, alignment, and on-site checks to keep rigs productive.

Trencher with carbide teeth cutting stabilised wall

Trencher Repair & Modification

Carbide teeth and side cutters increased shoe life by ~5x, eliminating hourly change-outs and cutting downtime on a stabilised wall job for Bachy.